How to Negotiate Snag Fixes With a Dubai Developer

How to negotiate snag fixes with a Dubai developer using an independent property inspection report

t was 9:40 on a Wednesday morning in October, on the eleventh floor of a two bedroom apartment in Jumeirah Village Circle.

Farhan had just finished the balcony door water test when the owner showed us an email on his phone. The developer’s handover team had replied to his first list. They would fix “the valid items” and close the rest as cosmetic.

His question was simple. “They have accepted about a third of it. How do I negotiate snag fixes without starting a fight?”

Farhan put the moisture meter down. “Let us start with what the water is doing.”

We hear some version of this on most handovers. A developer saying no to part of a snag list is common, and it is rarely the end of the story. This guide shows how to do it calmly, with evidence, and in writing.

To negotiate snag fixes with a Dubai developer, put every item in writing with a photo, room and location. Rank items by safety, function and finish. Ask for a dated rectification schedule, walk the disputed items on site with their engineer, and verify the work with a re-inspection before you accept anything as closed.

How to negotiate snag fixes with a Dubai property developer

Can You Actually Negotiate Snag Fixes With a Dubai Developer?

Yes. But “negotiate” here does not mean haggling.

Under your Sale and Purchase Agreement (SPA), the developer is expected to deliver the unit to the agreed specification. Real defects are part of that obligation. They are not a favour.

What you are really negotiating is scope, priority, method and timing. For a first time off-plan buyer, that shift in thinking makes the whole conversation easier.

What the developer is usually obliged to fix

The baseline is the SPA specification and the approved drawings. Electrical, plumbing, drainage and AC systems should work. Water should stay outside. Doors, windows and fixtures should operate as intended.

After handover, the developer also carries repair obligations during the defects liability period. We cover that in the escalation section below.

What is open to discussion

Some things genuinely are up for conversation. Finish tolerances, for example. Whether a tile is replaced or patched. Which items get done first, on which dates, and when the team can get access.

Being flexible on these points often makes the developer more flexible on the items that matter.

Before You Talk: Build a List the Developer Cannot Wave Away

A snag list, known in other markets as a punch list, is only as strong as its weakest line. The quality of your list decides most of the outcome when you negotiate snag fixes. In our experience, a numbered item with a photo and a location gets answered. A long paragraph usually does not.

What a strong snag item looks like

Each item should have:

  • A number that never changes
  • The room and exact location, such as “master bathroom, left of the vanity, 30 cm above the floor”
  • A clear photo
  • A one line description
  • Why it matters, for example water ingress or electrical safety
  • A reference where one exists, such as the specification or the manufacturer’s installation guidance

Our snagging reports follow a 250+ checkpoint checklist and arrive within 24 to 48 hours. We use thermal imaging and moisture meters so items like hidden damp come with readings, not opinions.

Separate defects from preferences

Be honest with yourself here. A paint shade you dislike or a design choice you would have made differently is not a defect.

Keep those off the main list, or in a separate short note. If preferences are mixed in, the real items get buried, and the developer has an easy reason to dismiss the whole document.

Keep one master list and version it

Pick one channel. That might be the developer’s portal, the handover desk email or a customer care reference number. Send everything there.

Keep one master list, update it, and date each version. A verbal promise on site is not a record until it is in an email.

Rank Your Snags So the Important Ones Get Fixed First

A long list with no order invites the developer to pick the easy items. Ranking is the quickest way to negotiate snag fixes without arguing over every line. A ranked list tells them where to start. Here is the three tier method we use with owners and investors.

TierWhat goes hereExamplesWhat to ask for
Tier 1: Safety and waterAnything that can hurt someone or let water inUnearthed socket, balcony threshold leak, moisture behind tiles, loose balustradeFix before keys, or a firm date within days, then a re-check
Tier 2: FunctionThings that do not work as they shouldAC not reaching set point, doors not closing, slow drains, faulty appliancesA dated plan, fixed before or soon after handover
Tier 3: FinishVisual items inside the unitPaint marks, grout gaps, chipped skirting, scratched glassA batch date or a joint walk, can move into the DLP in writing

Why the order matters

A developer’s site team is limited. When you show them clearly which items involve water ingress or safety, those usually get done first.

It also shows you are being reasonable. That goodwill helps when you reach the disputed Tier 3 items later.

If your list feels too long to sort, we can help you see which items matter most during a handover snagging inspection.

How to Put Your Request in Writing

Most owners who try to negotiate snag fixes lose ground not on the facts, but on the paperwork. A calm, structured email does more than a heated phone call.

Step by step

  1. Send the full report as one numbered list through the developer’s official channel.
  2. Lead with the Tier 1 items and say briefly why each one matters.
  3. Ask for written acknowledgement of each item number.
  4. Ask for a rectification schedule showing the item, the action, a target date and a re-check date.
  5. Propose a joint walk with their site engineer for any disputed items.
  6. Confirm every phone call or site agreement by email the same day.

That last step is the one people skip. It is also the one that saves them later.

Sample wording

Here is a line many owners adapt:

“Please find attached our independent snagging report with 112 numbered items. Items 1 to 9 involve water ingress or electrical safety, so we would be grateful for a date for these first. Could you confirm which items you accept and share a target date for each?”

It is polite, specific and easy to answer. That is the point.

Independent snagging inspection in a Jumeirah Village Circle apartment

What to Do When the Developer Rejects Items

Rejections usually come with one of a handful of reasons. Each has a calm, practical reply, and knowing them in advance makes it easier to negotiate snag fixes item by item.

“It is cosmetic”

Ask one question. Does the item affect water, safety, function or the life of the material?

A hairline gap in silicone around a shower tray looks cosmetic. It is not, because water gets behind it. If the answer is yes, show the evidence. We have written more on what to do when a developer says snags are just cosmetic.

“It is within tolerance”

When a developer says an item is within tolerance, it is fair to ask which tolerance, and to see it in writing.

Then measure. A level across a floor, a gap gauge on a door or a moisture reading on a wall turns a debate into a number.

“It is the design”

Check the SPA specification, the brochure and any approved finishes list. If the design matches what was sold, accept it and move on. If it does not, point to the page.

“We will offer cash instead”

A cash offer is a choice, not a duty. Before accepting, understand what you may be giving up, such as a later claim on that item. Our guide on what happens when a developer offered cash instead of fixing snags covers the trade-offs.

“We do not accept outside reports”

You do not need them to accept the company. You only need them to look at each item.

Offer a joint walk. A defect is still a defect, whoever wrote it down.

A Real Example From a JVC Apartment

Back in the JVC apartment, Farhan sat down with the owner and his 112 item list.

He moved nine items to the top. Every one involved water or electrical safety: the balcony threshold letting water in during the hose test, a high moisture reading behind the guest bathroom wall, and a socket with no earth.

Tier 2 held a kitchen cabinet door that would not close, a noisy AC return grille and a slow basin drain. Tier 3 was paint touch ups, grout gaps and one chipped skirting.

The owner sent a new email. Tier 1 first, each item numbered with photo, room, location and a short reason. He asked for a dated plan.

Within the week, the handover team accepted all Tier 1 items and most of Tier 2. The disputed Tier 3 items were reduced to a short list, agreed on site with the developer’s engineer.

That was the first half. The second half is checking the work. When the developer says the job is done, it helps to re-inspect after the developer fixes snags so you know what is really closed.

When Talking Stops Working: Your Escalation Options in Dubai

Most owners who negotiate snag fixes settle the list with clear evidence and a joint walk. Some do not. Here is the calm route forward.

Check your SPA first

Read the defects clause, the snag window, the handover procedure and the dispute clause. The dispute clause tells you whether disagreements go to the courts or to arbitration. It is worth knowing before you need it.

The defects liability period still protects you after handover

Items that are not fixed before handover do not simply disappear. The defects liability period (DLP) commonly covers non-structural and MEP defects for one year, and structural defects carry ten year liability.

Dubai Law No. 6 of 2019 is commonly summarised as setting one year for installations from handover and ten years for structural parts from the completion certificate. Sources differ on start dates, so check your SPA and assume the earlier date applies.

Under Dubai Law No. 8 of 2007, the escrow agent also keeps 5 percent of the project escrow account for a year after units are registered. You cannot claim that fund directly, but it is one reason developers stay engaged during the first year.

The Dubai Land Department and the courts

Buyer and developer contract disputes go through the Dubai Land Department, which offers an amicable settlement route. If that fails, the matter can go to Dubai Courts, or to arbitration if your SPA says so.

The Rental Disputes Centre deals with tenancy matters. It is not the forum for a sale contract defect dispute.

Keep paying what the SPA requires

Stopping a scheduled payment over snags can allow the developer to use its remedies under Dubai Law No. 13 of 2008, as amended by Law No. 19 of 2017, after a notice through the DLD. That is a serious risk for a list of fixable items.

Speak to a lawyer for your specific contract.

Frequently Asked Questions

Can you negotiate snag fixes with a developer in Dubai?

Yes. The developer is expected to deliver the unit to the agreed specification, so real defects are not up for debate. What you can discuss is the order of works, the repair method, the dates and how disputed items are checked. A written, numbered list makes that conversation much easier for both sides.

Will a Dubai developer accept an independent snagging report?

Most developers will review an independent report if the items are clear. They may not agree with every line, but a numbered item with a photo, a location and a reason is hard to ignore. Offering a joint walk with their site engineer usually helps settle the disputed items without a long email chain.

How long does a developer have to fix snags in Dubai?

There is no single deadline for every project. The timeline usually comes from your SPA and the developer’s handover process. That is why asking for a written schedule with a date per item matters. Items that are not closed before handover can still be raised within the defects liability period.

Should I sign the handover form if snags are not fixed?

Read the form carefully before signing. Many owners sign with the agreed snag list attached and a note that the listed items remain open, rather than signing that the unit is accepted in perfect condition. Wording matters here, so speak to a lawyer for your specific contract if you are unsure.

What if the developer says a snag is only cosmetic?

Ask whether the item affects water, safety, function or how long the material will last. If it does, show the evidence, such as a moisture reading or a failed water test. If it truly is visual only, it may still be worth fixing, but it makes sense to rank it lower.

What happens to snags that are not fixed before handover?

They do not disappear. Keep them on a written list that the developer has acknowledged, with dates. Non-structural and MEP defects are commonly covered for one year under the defects liability period, and structural defects for ten years. Check your SPA, and assume the earlier start date applies.

Can I re-inspect after the developer says the snags are fixed?

Yes. A re-inspection checks each item against the original report and marks it closed, reopened or partly fixed. It is booked as a separate visit, so ask for the fee when you book. It is the simplest way to avoid items being closed on paper only while the defect stays in place.

Can I negotiate snag fixes if I live outside the UAE?

Yes. Many overseas owners give access to an inspector, receive the report digitally within 24 to 48 hours and send it to the developer by email. A family member or agent with the right authority can attend the joint walk. Keep every agreement in writing, the same as you would in person.

How the JVC Handover Ended, and How We Can Help

Three weeks later, the owner booked a re-inspection with Farhan.

Most Tier 1 and Tier 2 items were properly closed. Two were reopened because the fix had only been painted over, and the developer came back for them. A handful of finish items moved into the DLP with written dates.

No drama. No lawyer letters. Just a list the developer could work from.

As Mohammed Nadeem Maldar, our Engineering Manager, often puts it: “We do not repair anything and we have no link to any developer, so our job is simply to describe what we found clearly enough that someone can fix it.”

At Prime Inspections & Snagging, we inspect and report. That is all. Our RERA certified, DLD approved inspectors have carried out more than 73,000 inspections across Dubai and the wider UAE.

If you have a handover date coming up, we can inspect the unit and give you a numbered report you can work from. Handover snagging starts from AED 999 for a studio or one bedroom and from AED 1,499 for a two bedroom, excluding VAT.

When the developer says the work is done, we can come back and check. That re-inspection is booked as a separate visit, so ask for the fee when you book.